Change workloads between tests

  • Yinglong
  • Yinglong's Avatar Topic Author
15 Jul 2013 09:40 #1281

I completed a test with Medium workload, when I try to change the workload to Light for the next test, it doesn't seem to change. See attached screenshot. The workload is changed in "test setup" to Light, but still showing as Medium in "start test" page. Is there anywhere I can save the change? Thanks.

Attachments:

Please Log in to join the conversation.

More
15 Jul 2013 09:53 #1282

Hi Ying,

It does indeed not change the MMC/Dashboard (known bug). You can safely ignore this in the MMC/Dashboard.
The workloads selected from the pull-down menu will be performed in every session (see progress bar). Thanks,


Omar

Please Log in to join the conversation.

  • Yinglong
  • Yinglong's Avatar Topic Author
15 Jul 2013 09:59 #1284

Hi, Omar:
Is it correct the actual work load applied in the test sessions would be the one that in the test log file folder? ie. if the file "light.txt" in the log folder, the light workload will apply for the test?

Thank you

Please Log in to join the conversation.

More
15 Jul 2013 10:00 #1285

Hi Ying,

Correct =)

Yw.

Please Log in to join the conversation.

Start Delivering the Best End User Experience Today

Request a Demo

Login VSI, Inc.

3945 Freedom Circle
Suite 670
Santa Clara, CA 95054

Phone: +1 408 899 7418

300 Tradecenter
Suite 3460
Woburn, MA 01801

Phone: +1 408 899 7418

Login VSI B.V.

De Entree 85
1101 BH Amsterdam
The Netherlands

Phone: +31 20 705 1200